Electrical power lines carry an electrical current, whereas a magnetic field is produced from the conducting wire which induces an AC voltage into the buried pipe. This linking causes an alternating voltage and current to be induced onto a parallel collocated pipeline.
When a pipeline located near a power line, it is subject to several electrical effects depending upon the operational status of the line. In addition, a lightning stroke or other cause, the power line will experience a short circuit condition known as a fault. The focus of the AC predictive guide is based on inductive/conductive coupling and fault conditions from co-located power lines using ACPT.
Understanding AC circuits and prediction fundamentals is a must. (See TT’s Website on Training for AC Mitigation). The ACPT focuses primarily on inductive and conductive (resistance) and not on capacitive interference effects.
Electrostatic Interference:
Electromagnetic Induced Voltages:
AC Faults – Inductive & Conductive
AC mitigation is a way to reduce the effects of induction from the effects of AC power line interference. This is accomplished by using ground principles. See section 5 for more information.
Types of Mitigation or Grounding
AC Decoupling Devices, Polarization Cells, and Surge Protection
Mitigation to Meet NACE Standards
Gradient Control Mats at Pipeline (Personnel Safety)
Induced AC Potentials
Discontinuities – Physical Pipeline
Discontinuities – Electrical Tower Line
Additional data are required for the average tower ground resistance to remote earth and the average separation between the faulted transmission line towers (structures).
Cross-sectional height and horizontal displacement of the shield (sky) wires from the tower center line are evident inputs. Program default accepts data for two wires with the assumption that the wires are periodically grounded to the tower grounds. However, this is not always the case.
Physical placement of the wires, i.e., height and horizontal displacement from the tower center line are obvious when data are available. Default values for typical circuits as a function of circuit voltage level are available from within the program database.
Below are typical fault current values, separation tower distances for the circuit voltage in kV. There are four (4) primary power transmission line types: (See Appendix C for Field Data Requirements)
The tower voltages run from 69 kV to 550 kV. For example, if the tower voltages are lower than 69 kV, the 69 kV-100 can be used; however, the correct current load must be obtained from the power company.
Power transmission operating data are not always available from Power Companies. Although the program gives operating defaults, these values must be verified especially with day-to-day loads which directly impact the induced steady-state voltages on the pipeline. Below is a table that shows the ranking of the current loads on a pipeline right of way in Table 1.
Table 1 – Relative Severity of AC Interference
Fault conditions from co-located power lines also present inductive/conductive conditions on the pipeline. Below is table 2 that provides typical tower voltages, currents, and separation that are required for input to the ACPT program. These data should also need to be verified by the Power Company.
Table 2 – Tower Circuit Fault Voltages and Currents
Barnes layer data are set up to represent the bulk soil multiple layers for the corrosive layer (pipe depth), apparent layer (steady-state and inductive fault), and conductive layer (conductive fault). Other considerations include:
Note: Barnes Layer – Below is a typical schematic of these three (3) major layers to consider bulk and specific layer resistivity. Any of these layers can be varied in depth depending on the geo layering and resistivity layers related to pipeline depth.
See attached as an example Excel Spreadsheet to set up multiple layers at the end of this manual.
Note: There are soil resistivity inversion programs that calculate a two-layer method based on field measurements and depths. Technical Toolboxes allows the user to select the methods of measurement and calculation methods for data input.
Example of Barnes Multi-Layer Soil Resistivity for AC Modeling and Mitigation:
Diameter
Coating Resistance (See Coating Resistance Tables in Section 2.9)
Depth of Cover per section
Soil Resistivities (See Barnes Layer Spreadsheet)
Pipe Sections (Manual) are shown below. (See section 7 (Users Guide) for additional information in setting up and adding sections).
Angles should be similar to pipeline angles i.e. section 1 (45 degrees ahead and to the left towards the power line. Section 3 (45 degrees ahead to the right).
Distances from pipe to tower should be based on which side of the pipe is relative to the power line i.e. (Section 1 is 50 feet from pipe to power line). Since there is a tower at section 2, it is the distance from pipe to tower i.e. 10 feet. Section 3 example is set -25 feet from pipe to tower.
The same concept applies to the remaining line sections 4, 45 degrees ahead to the left at -25 feet and section 5, 45 degrees right at -75 feet, etc.

Four (4) Types of Importing LAT./LONGS and GIS Data
For example, A map kmz. or kml. file was imported for both the Power Transmission Line and Pipeline as shown on the next page. Then point and click technology is used to create sections at nodes, towers, proposed mitigation sites, soil resistivity changes, transpositions, etc., Once this is completed, the user can calculate sections, distance, and angles.
The ACPT automatically calculates:
This workflow allows the user to import large data sets quickly for pipelines and AC transmission lines. By using Point and Click which sets up sections within minutes and identifies AC threats immediately start design mitigation strategies. If you need to put in an additional section or sections, just go back and insert with no limitations.