Electrolyte Resistance from Surface of an Electrode to any Distance
These circuits are used for measuring the resistance of solutions or gases to measure an ohmic IR drop through a material or solution.

𝑅 − Resistance to electrolyte(ohms)
𝜌 − Electrolyte resistivity(ohm⁄cm)
𝐿 − Distance through the electrolyte traveled by current,assumed 1cm.
𝑑 − Distance from the central electrode(cm)
𝐾𝑎 − Geometry factor for the central electrode
𝑟 = 𝐾𝑎𝜌
Some commonly used electrode arrays and their geometric factors. Note that for the multiple gradient array, the total array length is ‘(s + 2) a’ and the distance between the center of the potential dipole pair P1 – P2 and the center of the current pair C1 – C2 is given by ‘ma’.

Input Parameters
- To create a new case, click the “Add Case” button
- Select the Electrolyte Resistance from Surface of an Electrode to any Distance application from the Pipeline Corrosion list.
- Enter Case Name, Location, Date and any necessary notes.
- Fill out all required fields.
- Make sure the values you are inputting are in the correct units.
- Click the CALCULATE button.
- Electrolyte Resistivity(ohm-cm)
- Distance from the Central Electrode(cm)
- Geometry Factor for the Central Electrode

Output/Reports
- View the results.
- If an input parameter needs to be edited be sure to hit the CALCULATE button after the change.
- To SAVE, fill out all required case details then click the SAVE button.
- To rename an existing file, click the SAVE As button. Provide all case info then click SAVE.
- To generate a REPORT, click the REPORT button.
- The user may export the Case/Report by clicking the Export to Excel/PowerPoint icon.
- To delete a case, click the DELETE icon near the top of the widget.
- Resistance of Electrolyte(ohm)

Related Links
Table of Contents
Table of Pages
Table of Contents
- Pipeline HUB User Resources
- AC Mitigation PowerTool
- API Inspector's Toolbox
- Horizontal Directional Drilling PowerTool
- Crossings Workflow
- Hydrotest PowerTool
- Pipeline Toolbox
- Encroachment Manager
- PRCI AC Mitigation Toolbox
- PRCI RSTRENG
- RSTRENG+
- Ad-hoc Analysis
- Database Import
- Data Availability Dashboard
- ESRI Map
- Report Builder
- Crossings Workflow
- Hydrotest PowerTool
- Investigative Dig PowerTool
- Hydraulics PowerTool
- External Corrosion Direct Assessment Procedure - RSTRENG
- Canvas
- Definitions
- Pipe Schedule and Specifications Tables